Energy
Oklo Finalizes Multi-Year HALEU Supply Contracts With Centrus

Key PointsOklo's prepayments help Centrus finance new domestic enrichment capacity for HALEU…
View more
- Oklo's prepayments help Centrus finance new domestic enrichment capacity for HALEU deliveries.
- Meta's power prepayment lets Oklo fund fuel purchases for its planned Ohio campus.
- The definitive contracts formalize earlier intent without changing reactor coverage or delivery timing.
Oklo announced definitive, multi-year fuel-purchase contracts with Centrus Energy (LEU ) on November 12, 2026, committing to prepayments for future high-assay low-enriched uranium (HALEU) deliveries that will help finance new U.S. uranium-enrichment capacity.
The agreements cover enough HALEU to support up to five Aurora powerhouses for multiple years. Deliveries from Centrus’ American Centrifuge Plant in Pike County, Ohio, are scheduled to begin in 2029. The supply also covers future Aurora deployments and later refueling of the Aurora powerhouse at Idaho National Laboratory.
That supply extends Oklo’s fuel arrangements beyond its first reactor in Idaho, which already has an allocation of recovered Experimental Breeder Reactor II fuel.
Meta Power Funding Supports Fuel Procurement
Meta’s prepayment for future Oklo power production supports the HALEU purchase for the first phase of the planned 1.2-gigawatt Ohio campus. The agreement Oklo and Meta announced on January 9, 2026 created a mechanism for Meta to prepay for power and provide funding to advance Aurora deployment. Oklo said at the time that it would use the funds to secure nuclear fuel and advance Phase 1. The Centrus prepayments apply that mechanism to the fuel supply chain.
The campus is planned for 206 acres that Oklo owns in Pike County, on land formerly owned by the Department of Energy. It is intended to support Meta’s regional data-center operations while adding generation to the Ohio grid. Pre-construction and site characterization were slated to begin in 2026. Oklo targets the first phase coming online as early as 2030, followed by incremental expansion to the campus’s full capacity by 2034.
Definitive Terms Replace Earlier Intent
The contracts formalize a letter of intent announced on June 18, 2026, which anticipated a further definitive agreement and said the arrangement could include Oklo prepayments. The June outline already contained the same reactor coverage and delivery start. The new development is therefore the definitive purchase commitments and committed prepayments, rather than a revised scope or timetable.
Centrus said it has secured $5.4 billion in customer contracts and commitments to purchase low-enriched uranium and HALEU from the new capacity. President and Chief Executive Officer Amir Vexler tied the financing to the company’s manufacturing scale-up: “Oklo’s prepayments, which add to the others we have previously received, will help fund our buildout as we scale Centrus’ proven American Centrifuge technology and qualified manufacturing processes for commercial production.”
The immediate consequence is financial rather than operational: Meta’s power prepayment is helping Oklo fund fuel purchases, while Oklo’s prepayments help Centrus build the capacity needed to deliver that fuel. The scheduled delivery start and the first-phase operating target are the milestones that will show whether this sequence produces an operating Ohio campus.