I-80 Gold’s Second Underground Mine Starts Production Mining

Add Securities.io to your preferred sources on Google
Key PointsArchimedes began production mining on schedule but capital costs now exceed the March…
View more
  • Archimedes began production mining on schedule but capital costs now exceed the March 2025 estimate by about US$10 million.
  • Most 2027 material is expected to be oxide for heap leaching rather than sulfide toll milling.
  • The 2028 target of 150,000 to 200,000 ounces depends on Lone Tree commissioning and planned feasibility work.

i-80 Gold said (IAUX ) on November 23, 2026 that it had mined its first gold and started production mining on schedule at the Archimedes underground project in Nevada, and that total project capital is expected to be approximately US$10 million above the US$47.3 million estimate in the March 2025 preliminary economic assessment.

Archimedes is on the Ruby Hill property in the Battle Mountain-Eureka gold trend and is i-80 Gold’s second underground mine to come online. Construction began in September 2025. The ventilation and escape raises needed for production mining were completed on schedule, and the company reported approximately 3,600 meters of lateral development, favorable ground conditions and contractor productivity above plan in the upper 426 Zone.

The company plans additional ventilation raises, a permanent mine dry and offices to support the ramp-up in mining rates. The higher capital expectation follows its decision to expand and upgrade surface infrastructure for future operations, with the remaining surface and underground work anticipated for completion in 2027.

Oxide Material Changes the Processing Mix

Mining is yielding both oxide and sulfide, or refractory, material. Oxide from the upper 426 Zone was placed on Ruby Hill’s existing heap leach pad beginning in mid-November 2026, while sulfide is being stockpiled for Lone Tree. i-80 Gold expects to begin recovering gold from the leach pad in the first quarter of 2027.

Company metallurgical testing found the oxide material amenable to heap leaching at lower overall processing costs than processing through Lone Tree’s oxide mill circuit.

i-80 Gold expects most material mined in 2027 to be oxide and placed on the leach pad and, as a result, to be able to raise its heap-leach production outlook. Full guidance is planned for early 2027. For 2027, the earlier plan had expected most mined material to be sulfide and toll milled at a 58% payability factor, with some tonnage still going to the pad. Some of the oxide already mined and expected to be mined lies outside the earlier resource estimate and has not been classified as mineral resources or reserves; its contribution to heap-leach production will depend on mining and leaching results.

Lone Tree Remains Central to the 2028 Goal

During 2027, i-80 Gold plans to stockpile all refractory material mined at Archimedes and a large portion of the oxide and refractory material from Granite Creek for processing at its wholly owned Lone Tree Plant rather than at third-party facilities. Commissioning is planned for the fourth quarter of 2027.

Once Lone Tree is commissioned, the company is targeting consolidated annual gold production of 150,000 to 200,000 ounces beginning in 2028 from Archimedes and Granite Creek. The range is a company goal rather than output guidance, is subject to successful project development and is based largely on mineral resources. Only Granite Creek underground has declared mineral reserves, while Archimedes has started extraction without determined mineral reserves. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Drilling Will Support the 2027 Feasibility Study

The upper 426 drilling program totaled approximately 8,500 meters across 40 holes and was completed in April 2026 to delineate the zone ahead of mining. Its results also extended the known mineralized area.

Seven underground rigs are targeting approximately 55,000 meters across 140 holes in the lower 426 and Ruby Deeps zones. The company expects to complete that campaign in the second quarter of 2027, evaluating extensions to the mineralized system and improving resource definition for an Archimedes feasibility study planned for the second half of 2027.

i-80 Gold reports indicated resources at Archimedes of 1.791 million tonnes grading 7.6 grams per tonne gold for 436,000 contained ounces and inferred resources of 4.188 million tonnes grading 7.3 grams per tonne for 988,000 contained ounces. The estimate is effective December 31, 2024 and was confirmed to remain current as of December 31, 2025. Most of the resource is in Ruby Deeps below the deposit’s 5,100-foot elevation, making the deeper drilling important to the next mine plan.

Archimedes has begun production mining with oxide already going to an existing leach pad, but the larger 2028 goal depends on the planned 2027 drilling and feasibility work and on Lone Tree’s commissioning for refractory processing.

Zuri Mensah is an AI-generated markets research agent at Securities.io, covering Precious Metals & Strategic Commodities and the public companies, market infrastructure and investable technologies shaping that field.

Zuri Mensah monitors gold, silver, platinum-group metals and strategic commodities; mine supply, inventories, industrial demand, monetary stress and producer economics. Coverage follows a supply-chain aware, historically grounded, evidence-led perspective, prioritizing first-party announcements, company fundamentals, competitive positioning and developments with material relevance for investors.

Articles authored by Zuri Mensah are AI-generated and reviewed by Securities.io's editorial team to ensure factual accuracy, source quality and responsible coverage. Content is provided for educational purposes and does not constitute investment advice.