Drax Signs Brookfield and Radiant Deal for Yorkshire AI Data Center

Key PointsThe £20 billion figure is potential development investment contingent on a build-out…
View more
- The £20 billion figure is potential development investment contingent on a build-out far beyond phase one.
- Phase one still hinges on securing a tenant and final investment decisions before any construction begins.
- Drax's biomass subsidy mechanism could let up to 500MW of generation serve the data center if approved.
Drax Group announced on November 3, 2026, that it had signed an agreement with Brookfield and Radiant to jointly develop, deliver and operate an AI data center at Drax Power Station in North Yorkshire. Brookfield estimates that total potential investment in the full development, including semiconductor chips, could exceed £20 billion, with an initial £2.5 billion as part of the first phase. Those figures describe potential development investment, not expenditure already incurred.
Drax is targeting more than 1GW of capacity across three phases. The first would provide up to 100MW of compute capacity and is planned to be operational in the first quarter of 2028. Phase two is an ambition to add 500MW between 2028 and 2031, with further capacity contemplated after 2031. The full investment estimate therefore depends on a build-out well beyond the initial phase.
Radiant, Brookfield’s UK-headquartered AI infrastructure platform, will lead design, customer engagement and commercialization. Drax will lead land, power integration and planning, while investment capital and operating capabilities are to come through the Brookfield-Qai joint venture.
The funding vehicle predates the UK agreement. Brookfield and Qai announced it on December 9, 2025, as a $20 billion joint venture focused on AI infrastructure in Qatar and select international markets. Brookfield and its partners planned to invest through the Brookfield Artificial Intelligence Infrastructure Fund, within a global program aiming to mobilize up to $100 billion.
Existing Power Infrastructure Shapes the Build-Out
The project draws on infrastructure already at the power-station estate: more than 1,000 acres, approximately 4GW of grid access, 2.6GW of active dispatchable generation and cooling systems. Drax identifies its location beside one of the UK’s largest substations and its proximity to the UK fiber network as additional development advantages.
Phase one would import electricity directly from the grid through existing infrastructure managed by Drax. The later phases instead contemplate a behind-the-meter arrangement, using existing Drax generation to supply around-the-clock power directly to the data center under a long-term power purchase agreement, subject to consents. The two supply models connect the initial schedule to grid approvals and the larger expansion to consents for direct supply from Drax’s generation.
Those arrangements intersect with Drax’s biomass Contract-for-Difference signed with the UK Government in November 2025. It covers approximately 6TWh of generation annually from April 2027 through March 2031, about 30% of annual baseload output from the station’s active generation. The agreement contains a mechanism for Drax to request that up to 500MW be used to power a data center during that period. Any such use requires agreement from the government and the Low Carbon Contracts Company after consideration of consumer value for money, energy security and sustainability. Drax says the station’s security-of-supply role, low-carbon dispatchable power and critical system services will remain unchanged.
Tenant and Approvals Remain Outstanding
The initial phase remains subject to planning, regulatory and network approvals, securing an acceptable tenant, negotiating necessary commercial agreements and a final investment decision by each party. Radiant is seeking anchor customer commitments before starting construction. The partners are preparing a planning application and expect public consultation to begin in November 2026. They also expect to create a voluntary community benefits fund, separate from planning obligations and Drax’s existing community initiatives.
Drax CEO Will Gardiner said the project “can help secure the long-term future of the site and protect hundreds of jobs.” The signed agreement establishes the development team and a potential capital route, but not a construction start. Delivering the first phase now turns on tenant commitments, approvals and final investment decisions; the larger ambition additionally requires agreement over how the station’s generation can serve the data center while preserving its stated system role.